Before first snowfall near the city of Minsk (Belarus) two tennis courts were covered with DBS Plus membrane system. Air dome dimension 72.32×19.3×9.5 m is equiped with 3 regime lighting system, which enables illuminance on pitches of 100 lx, 300 lx and 500 lx. Air dome/inflatable hall is heated with machinery unit with 450 kW of heating capacity, which can ensure warm indoor ambient in the coldest winter. Machinery units are equiped also with additional chiller module with 100 kW capacity for summer use, when cold air must be inflated inside the dome.
Sports dome installation with all equipment (membrane and lighting system, entrance elements, machinery units, dividing nets and all additional components) was installed in just 6 days, despite windy conditions during installation.